Name of the Client:
Haldia Development Authority (HDA) Haldia , West Bengal.
Brief description of the Project:
Funding Agency: Haldia Water Management Limited (SPV between JUSCO & Ranhill Berhad, Malayasia)
Contract Value of JUSCO EPC: 389.6 (Rs. Million)
Contract Duration: 24 months
Date of Completion: April '10
Salient Features of the Project:
- Rehabilitation, Operation & maintenance of the existing 113.5 MLD water treatment plant, service of tube well ( 13.62 MLD) & existing pipe network.
- Construction of new 113.5 MLD water treatment plant in 2 equal modules based on Dissolved Air Floatation technology (DAF) followed by O&M of the plant.
- Construction of intake structure on river Haldi.
- Construction of Raw, Settled & Clarified water pump house.
- Laying of conveyance main for raw water.
- Billing and collection from consumers.
|